How long does an ERPNext implementation take?

A core go-live usually takes 4 to 12 weeks; factories and multi-branch companies may need 3 to 4 months. It is better to go live in phases than to switch everything on at once.

Short answer: A core go-live usually takes 4 to 12 weeks; factories and multi-branch companies may need 3 to 4 months. It is better to go live in phases than to switch everything on at once.

Typical phases

  • Process review with each department (1–2 weeks)
  • Setting up accounts, inventory and permissions (2–4 weeks)
  • Data and opening balance migration (1–2 weeks)
  • Training and trial run (1–2 weeks)
  • Go-live, then follow-up

What makes it longer?

  • Messy item and customer data
  • Lots of customisation before trying standard features
  • No decision-maker on the client side
  • Trying to launch every module at once

How to shorten it

Start with the modules that solve your biggest problem now, such as sales, inventory and accounting, then add manufacturing or payroll in phase two. Your team sees results in weeks, not months.

Read also Why do ERP projects fail?

Questions we hear a lot

Do we stop working during implementation?

No. We work alongside your current system and switch over on a set date after training and testing.

When is the best time to go live?

The start of a month or a financial year, so opening balances are clean.